Wednesday, July 23, 2008



We have begun preparing for the interior slabs and have poured this 3,000 square foot section already. We will be doing 2 pours a week.



As this picture shows, we have completed the erection of the structure down French Broad Street and have turned the corner. This photo shows the height of the building at its highest point, the fifth floor element of the main penthouse.

Monday, June 16, 2008

The structure began going up two weeks ago. This picture is about a week old, so it only shows about half of the progress. Thi section is the corner of French Broad and Caldwell.It is built up to the roof and is a bit longer to the left in this picture.

Saturday, May 24, 2008



It's very impressive, probably the biggest crane that has been used in Brevard!


The crane has a 230 ton capacity and the boom is 200 feet long. It will set in the area of the parking structure until it has completed the building, and then it will move out to the alley and build the parking structure.

Thursday, May 22, 2008

By May 20, 2008 we finished the on-grade foundation, and the entire site had been graded to finsh elevations and covered with gravel. The crane for the erection of the building was delivered on the 20th and it tooke two days to off load the parts and put it together. This is a brand new crane just delivered into the U.S. to Davis Erecting out of Greenville SC.

Tuesday, April 15, 2008



Concrete pump used to pour the footers. There will be approximately 2,000 yards of concrete in the foundation, half of which is in the pilings that are finished.