Saturday, May 24, 2008



It's very impressive, probably the biggest crane that has been used in Brevard!


The crane has a 230 ton capacity and the boom is 200 feet long. It will set in the area of the parking structure until it has completed the building, and then it will move out to the alley and build the parking structure.

Thursday, May 22, 2008

By May 20, 2008 we finished the on-grade foundation, and the entire site had been graded to finsh elevations and covered with gravel. The crane for the erection of the building was delivered on the 20th and it tooke two days to off load the parts and put it together. This is a brand new crane just delivered into the U.S. to Davis Erecting out of Greenville SC.