Thursday, September 11, 2008



Here are a couple of view shots.


This is a dated photo but it shows the primary corner well.


On September 8, 2008 Davis Erecting set the last piece of the precast structure. On the night of the ninth the crane was disassembled and removed that night and the next day. The structure is complete, and now we have begun the upfit of the interior. We have poured about 80% of the interior slabs on the 2nd 3rd and 4th floors and have begun the plumbing. One of the stairwells is completed and access is much easier. We have moved the fences out the the street sides to begin leveling out the exterior so that the windows and balconies can be placed. Those items will begin around the end of the month.